Ecomar Jetty lines extension & connectivity to POF MM1
- EPC of BO & GO pipelines extension to connect with MM-1 facility in POF FOTT.
- 24” &20” BO & GO pipelines supply, fabrication, testing, painting, installation & commissioning
- 8” N2 Line supply, fabrication, testing, painting, installation & commissioning
- Firefighting network, design, supply, fabrication, installation & commissioning
- Supply, installation, integration & commissioning of DBB-MOV’s, BF & Gate valves
- Civil & Structural works for the new facility